PADUCAH, Ky. —
Crews scooping out Mississippi River bedrock in southern Illinois are making steady progress but have removed just a fraction of the rock pinnacles that are impeding navigation along a stretch of the drought-plagued waterway, an Army Corps of Engineers official said Wednesday.
Excavating machinery had chiseled away 39 cubic yards of rock by Tuesday morning, less than 5 percent of the amount of pinnacles to be removed in coming weeks near Thebes, Ill., corps programs director Edward Belk told an inland waterways advisory board. One cubic yard amounts to a load three feet wide and deep.
Work started Sunday to remove the treacherous rock pinnacles along a six-mile stretch of the river where barge traffic is threatened because the river’s water level is so low between St. Louis and Cairo, Ill. The pace of rock removal should pick up with a second contractor joining the effort.
“We really have a sense of urgency to get this done,” Belk said in an interview afterward. “While we’re pleased with the contractors’ work, we’re not satisfied with any of this until we get it all removed.”
So far, crews are using excavating machinery to remove pinnacles, described as six times harder than concrete. Belk said he anticipates that explosives will eventually be used.
The emergency rock removal work is expected to continue until mid-January, Belk said.
The work stretches from 6 a.m. to 10 p.m. while the stretch of river is closed to shipping. Barges seeking passage line up for the eight-hour window when the stretch is reopened, with the U.S. Coast Guard essentially directing traffic, letting barges through in one direction, then the other.
The rock being removed typically would be beneath sand on the river bottom but has been exposed by the corps’ dredging efforts to keep the channel open.
Larry Daily, chairman of the Inland Waterways Users Board, said he was pleased with the corps’ efforts, noting the project was initially planned to start in February.
“Thirty days ago they were still in the mode of ‘Well, we’re going to wait and go through the normal procurement process, it will be 75 days before the contractor can start.’ And we changed that,” Daily said afterward. “If we could figure out how we did that and do it again, I’d like to bottle that.”
The rock removal project was expedited at the urging of lawmakers and others from Mississippi River states. The industry-based advisory group headed by Daily makes recommendations to Congress and the Army secretary on priorities for the Inland Waterways Trust Fund.
When the emergency project ends in mid-January, it will be followed immediately by work to widen that same stretch of channel by removing additional rock to make it safer for vessels, Belk said. The corps expects to award that contract next month, he said.
The work comes as the middle Mississippi River approaches historic lows due to months of drought. The situation was worsened last month when the corps cut the outflow from an upper Missouri River reservoir, further reducing the amount of water flowing into the Mississippi.
Besides rock removal and dredging, the corps also has allowed some lake releases into the Mississippi to add to the waterway’s depth. Belk told the advisory group that there’s one more key part of the strategy: “Pray for rain.”
Business
Crews make progress with Mississippi rock removal
- Business
-
-
A late fade on Wall Street; Wal-Mart, Disney slump
Signs of a slowing economy combined with comments from a Federal Reserve official helped pull the stock market down Thursday.
-
American will favor passengers without roller bags
If you’re traveling light, you can board earlier on American Airlines.
-
Bill would limit lawsuits over lead contamination
A Missouri-based lead mining company could be shielded from punitive damages in state lead contamination lawsuits under a bill sent to Gov. Jay Nixon.
-
Senate panel considers labor board nominees
Senate Republicans said Thursday they would not support five nominees to the National Labor Relations Board, raising the possibility the troubled agency could be rendered mostly inoperable later this year.
-
Missouri lawmakers pass changes to workers’ comp claims
Missouri lawmakers gave final approval Thursday to a measure that would double the fees charged to businesses in order to replenish an insolvent fund for disabled workers who suffer serious job-related injuries or illnesses.
-
Work could begin soon on new Interstate 44 interchange east of Joplin
Construction of a new interchange at Interstate 44 and Prigmore Avenue to serve the Crossroads Center Business and Distribution Park was added Thursday to the Transportation Improvement Program for Southwest Missouri.
-
Dow to appeal $1.2 billion damages order
A federal judge is ordering Dow Chemical Co. to pay $1.21 billion in damages after it lost a class-action lawsuit that accused it of conspiring to fix prices.
-
Weak open on Wall Street; Wal-Mart disappoints
Wal-Mart led the Dow Jones industrial average lower early Thursday after the world’s largest retailer turned in weaker sales and a dim forecast for profits.
-
Tennessee senator: Sale idea cost TVA $500 million
Sen. Lamar Alexander says President Barack Obama’s plan to consider selling the Tennessee Valley Authority has already cost hundreds of millions of dollars — even if the nation’s largest public utility is never sold.
-
Google’s products dig deeper into people’s lives
For Google CEO Larry Page, happiness is a warm computer.
- More Business Headlines
-