CARL JUNCTION, Mo. — The City Council and the builder of the new community center wrestled Tuesday night over how to proceed with the project after the contractor asked for a contract extension of 56 days.
Tony Smith, vice president of operations for Larry Snyder and Co., of Ozark, said the company since Nov. 16 had tallied 56 days in which at least 60 percent of the work that was scheduled for that day could not be completed because of rain, snow or other weather conditions.
He asked the council to consider adding 56 days to the company’s contract beginning April 1. A penalty of $500 per day would otherwise be assessed against the company.
Smith told the council that the delays were not the result of “neglect or not caring. It’s been weather. We’ve fought that since the end of October.”
Some council members were unhappy that work on the building has been drawn out longer than planned.
“I don’t feel like the city ought to eat everything,” said Councilwoman Dee Lynn Davey. “I know there has been weather, but you build that into a contract. I just kind of feel like the company needs to give a little bit here, too.”
Smith also asked the council to authorize $31,980 for a plastic material that would allow the company to proceed with construction of the parking lot and street despite wet soil conditions. He said the material, which he called a geogrid, would allow construction of the lot to begin almost immediately.
He said that if he was given the geogrid, the company probably wouldn’t need all 56 additional days to work on the building.
Under a suggestion by Davey, the council granted the contractor 28 weather days. The panel also agreed to purchase the geogrid.
A formal ordinance approving the change order would still have to be approved by the council, though Smith told council members to consider the agreement done.
“I’d move forward under those orders, absolutely,” he said.
Smith said the building last month was at least 79 percent complete. He said he thinks it will be 95 percent complete by April 1.
Work on the building, which voters approved through a $4.1 million bond issue in April 2008, began in early 2009. Because of several change orders, the total cost of the contract now stands at $4.26 million.
The center at 303 N. Main St. will house City Hall, a senior center, a gymnasium and meeting rooms.
In other business Tuesday night, the council approved a $146,000 purchase of new software for utility, tax, payroll and accounting operations from Tyler Technologies Inc. of Lubbock, Texas.
Police car
The Carl Junction council gave the go-ahead for the Police Department to purchase a new police car from Carthage Ford for $20,230 after a $5,300 trade-in.
Joplin Metro
Carl Junction council adds 28 days to contract to allow for weather delays on community center
- Joplin Metro
-
-
Longtime Democrat dies at 81
Sapp, 81, died Thursday. Funeral services were Monday at the First Presbyterian Church of Joplin. A longtime Jasper County Democratic committeewoman and volunteer, Sapp for years was secretary to the county’s central committee.
-
Motivational speaker offers free marriage course
Presented by Mark Gungor, the course is being offered free to the community. The event is being held to aid in tornado relief.
-
District sends faculty, administrators on site visits
With the design phase of several buildings in Joplin Schools ending in May, the district has sent 66 administration, faculty, parents and community members on site visits to 22 schools and two technology company headquarters across the country.
-
Mural depicting Joplin High School dedicated
A four-paneled mural depicting the recent history of Joplin High School was dedicated at the Memorial 9th- and 10th-grade Center Tuesday morning. The mural will be moved to the new high school when it is completed in 2014.
-
Carl Junction chamber creating new committees
The Carl Junction Chamber of Commerce is kicking off three new committees this week with meetings scheduled Tuesday and Wednesday.
-
Body of missing Joplin man found
The body of a missing Joplin man was discovered this afternoon inside his home in the Royal Heights neighborhood of Joplin.
-
Wildcat Glades nature center receives $50,000 grant
The Wildcat Glades Conservation & Audubon Center has received a $50,000 TogetherGreen Innovation Grant, which is being provided through an alliance between the National Audubon Society and Toyota.
-
Joplin shooting victim’s name released
The Joplin Police Department today released the name of a woman fatally shot in her home early Thursday and acknowledged that the shooting was reported as a suicide attempt.
-
Barry Manilow to deliver donated instruments
Singer-songwriter Barry Manilow will visit Joplin next week to donate more than $300,000 in musical instruments to replace those lost during the May 22 tornado.
-
Extreme Makeover releases names of families
"Extreme Makeover: Home Edition" has released more details about the build in the 2400 block of Connor Avenue, including the names of the seven families. They are:
- More Joplin Metro Headlines
-