Joplin school construction ‘continuing nicely’; safe room project begins

JOPLIN, Mo. — The recent arrival of cooler fall weather has not slowed work on the Joplin School District’s three major construction sites.

East Middle School remains the site that is further along than the others in the construction steps, Mike Johnson, the district’s director of construction, said late last week.

Crews are working on the foundation and beginning to form concrete walls. They’re also installing underground utilities, such as gas, water and electric lines. And the pipes sticking up out of the ground are in preparation for the slabs to be poured, he said.

But don’t expect many changes at the site in the immediate future.

“What I just said will be true for the next month or so,” Johnson said.

At the new Irving Elementary School, workers are relocating the sewer lines running through the site and drilling piers for the foundation.

At the high school site, workers have wrapped up utility work, which consisted of moving the gas, water, sewer and phone lines. Site excavation is “continuing nicely,” Johnson said.

Several bid packages — for steel and foundations at the high school and miscellaneous work at East — will be presented to the Board of Education at its meeting Tuesday, he said.

In other business, the district’s facilities committee last week received design plans for safe rooms to be built at Cecil Floyd, McKinley and Eastmorland elementary schools. The architect for those projects, as well as 10 additional safe rooms to be built at schools around Joplin, is PLJBD Architects and Engineers, of Joplin. Designs for the remaining 10 rooms have not been completed yet, he said.

Those designs ultimately will be submitted to the Federal Emergency Management Agency and the State Emergency Management Agency for approval. Federal and state funding — which will amount to 75 percent of project costs, with the district responsible for the remaining 25 percent — will be released after approval, Johnson said.

Designs for safe rooms at East and Irving have already been approved by FEMA and SEMA, he said. The submission and approval of the design for the safe room to be built at Joplin High School is under way, he said. Those safe rooms are being designed by the architectural firm that is handling each respective school: Hollis and Miller Architects, of the Kansas City area, for East; Sapp Design Associates Architects, of Springfield, for Irving; and Corner, Greer and Associates, of Joplin, for the high school.

Community access

Johnson said the safe rooms will be similar to a gymnasium, built according to FEMA standards and open to the community during inclement weather.

1
Text Only
Local News
  • Ballot issues dominate GOP event

    A maze of campaign yard signs lined the sidewalk at Big Spring Park, leading up to a line of local candidates for public office with rolled-up sleeves shaking hands with potential voters.

    July 24, 2014

  • Mike Pound: It’s time for some football

    The arrests, the announced suspensions and the contract disputes can mean only one thing: Somebody is ready for some football.

    July 24, 2014

  • Landfill opponents seek answers

    The Baxter Springs High School auditorium was filled with hundreds of Cherokee County residents Thursday night as Galena city officials answered questions and listened to comments regarding a proposed landfill at Riverton.

    July 24, 2014

  • Hanaway says leadership missing under Gov. Nixon

    When Republican gubernatorial hopeful Catherine Hanaway walked into the banquet room at Granny Shaffer’s Restaurant this week, she was greeted by some of Joplin’s more prominent business leaders.

    July 24, 2014

  • Neosho athletes bring home silver

    For 19-year-old Dominque Dechant, it was the trip of a lifetime. She and three other athletes from Neosho traveled last month to Newark, New Jersey, as part of the Missouri Special Olympics girls basketball team.

    July 24, 2014

  • r072414msw.jpg VIDEO: Carterville company expands to third generation

    What began as Ray “Mac” McCoy’s side job in his home 55 years ago has grown not only in square footage and reach, but in generations. This summer, a third generation took over the reins of MSW — Mac’s Specialty Woodwork — that now exceeds 90,000 square feet and creates custom furniture for chain restaurants coast to coast.

    July 24, 2014 2 Photos

  • Shrine Bowl band, cheerleaders, players arrive in Pittsburg this week

    Band members were the first Kansas Shrine Bowl participants to arrive at Pittsburg State University this week.

    July 24, 2014

  • Galena council rescinds landfill decisions

    The Galena City Council voted Wednesday to rescind decisions it made two weeks ago regarding a proposed landfill at Riverton.

    July 23, 2014

  • Miami council waives fees for barbecue event

    The Miami City Council voted Tuesday to waive $3,750 in usage fees for Miami Elks Lodge No. 1320 for an upcoming barbecue championship at the Miami Fairgrounds.

    July 23, 2014

  • Carthage prepares for Marian Days

    The 37th annual Marian Days celebration will start in two weeks, and planning is well under way for the event that will bring tens of thousands of Catholics of Vietnamese descent to Carthage.

    July 23, 2014

Must Read
Sports
Photos


Facebook
Poll

Amendment 8 in Missouri proposes a special lottery ticket to help fund state veterans homes. How will you vote?

For it.
Against it.
     View Results
Opinion
Twitter Updates
Follow us on twitter